Royal Navy's Type 45 project progressing well

An Equipment and Logistics news article

13 Mar 09

A report published by the National Audit Office (NAO) today on the Royal Navy's Type 45 destroyer programme says that while the project has suffered significant delays and escalating costs, more recently the project has progressed well, with key milestones being met.

Royal Navy Type 45 destroyer Daring

Royal Navy Type 45 destroyer Daring
[Picture: Crown Copyright]

The NAO report says that the project to deliver the new warships has been delayed by two years and that the costs have risen by some £1.5bn. It also says that Daring, the first ship of class, will enter into service without all elements of the new Sea Viper, formerly known as the Principal Anti-Air Missile System, in place.

The NAO says that the problems arose because of over-optimism about what could be achieved, inappropriate commercial arrangements and, in the early stages, poor project management, but goes on to say that the MOD has taken action to resolve these problems and in 2007 reviewed and renegotiated the ship contract with BAE Systems which subsequently merged with VT to become BVT. Since then, there have been no further cost increases or delays to the project and the project has progressed well, with key milestones, such as completion of sea trials, being met.

Tim Burr, head of the National Audit Office, said today:

"The early years of the Type 45 destroyer project were beset by problems. The Ministry of Defence is currently controlling costs and timescales successfully; but it now needs to focus on installing the other equipment the ships need to obtain their full capability and on getting to grips with developing an effective support solution to be ready in time to support these destroyers."

Defence Minister Quentin Davies, commenting on the National Audit Office report, said:

"The NAO rightly acknowledges the progress made with the Type 45 destroyer programme. Key milestones, such as completion of sea trials, have been met ahead of schedule. These are complex, sophisticated warships and where problems arose in the early stages MOD gripped the issue, renegotiated contracts where required and got the programme on track - the first of these impressive destroyers, Daring, sailed into Portsmouth, her future base port, in January this year.

Type 45 destroyer Daring

Type 45 destroyer Daring entering its home port of Portsmouth for the first time
[Picture: LA(Phot) Chris Browne]


"I have been following this programme closely since my appointment, and I am pleased to be able to say that progress with both building and sea trials is currently going very well. Four ships are in the water (Daring, Dauntless, Diamond and Dragon) while the other two vessels (Defender and Duncan) are well under construction and the powerful Sea Viper missile system has undergone two successful test firings. These ships will form one of the essential pillars of the Royal Navy in the 21st century."

Daring was originally due to enter service in 2007. Due to project difficulties, the contract was renegotiated and a revised in-service date of November 2010 was identified. Since the revised contract was agreed, all milestones and deliverables have been achieved on time or ahead of time and an earlier in-service date of the end of 2009 is being worked towards.

The remaining five vessels will enter service progressively through to the middle of the next decade.

The Sea Viper missile system has been successfully tested twice in the South of France and all elements of the system will be in place before Daring's first planned operational deployment.

Designed primarily to provide air defence protecting forces against enemy aircraft and missiles, the Type 45s are extremely versatile and able to undertake a broad range of missions from combat to humanitarian assistance.

Launch of Dragon

The new Type 45 destroyer Dragon being launched into the Clyde from BVT's shipyard at Govan
[Picture: LA(Phot) Simon Ethell]


The six ships are:

1. Daring - launched in February 2006 and completed her contractor sea trials in September 2008. She was handed over to the MOD from the shipbuilder BVT on 10 December 2008 and set sail from the Govan dockyard on the Clyde on 16 January 2009 for the journey down to Portsmouth, arriving at her base in Portsmouth on 28 January 2009.

2. Dauntless - launched in January 2007 and completed her first set of sea trials on 12 December 2008.

3. Diamond - launched in November 2007 and her first set of sea trials are scheduled to begin in summer 2009.

4. Dragon - launched in November 2008 and her first set of sea trials are scheduled to begin in 2010.

5 & 6. Defender and Duncan - both vessels are still being built and are due to be launched in late 2009 and late 2010, respectively.

Sea Viper, formerly known as the Principal Anti-Air Missile System, is a maritime area air defence system composed of the Sampson radar, which is immensely powerful and sophisticated. The system is designed to deal with multiple simultaneous attacks by the most advanced anti-ship missiles in existence or envisaged.

The MOD has extended the service life of the older Type 42s because of the delay in bringing the Type 45 destroyers into use. The Type 45 destroyers will provide much more capability than the Type 42s. In addition to being able to engage multiple hostile aircraft or missiles simultaneously, they will be able to carry a significant number of extra personnel, such as troops or evacuated personnel, on board. They will also have better accommodation for personnel, more fuel efficient engines and be able to operate the Lynx, Merlin and Chinook helicopters.



Jack Speak

DE&S News

News from the Defence Equipment and Support

Navy submarine sails after major upgrade

The nuclear-powered Royal Navy submarine HMS Triumph has set sail for sea trials...

11 Mar 10

New satellite will support UK military operations

Communications on the UK's military operations are to be boosted thanks to a...

11 Mar 10

'Tugs of the future' will support Navy's new carriers

As part of the £1bn Future Provision Marine Services contract, a brand new range...

8 Mar 10

New life-saving equipment for medics in Afghanistan

Armed Forces medics in Afghanistan are now able to use an innovative piece of...

2 Mar 10

Soldier toasts team behind Osprey body armour

A soldier whose life was saved by his body armour in Afghanistan has thanked the...

1 Mar 10

More DE&S stories

Visit the DE&S site

Page rated 1 times
This page has an average rating of 5/5